Progress Update on Drainage Work


CLICK HERE TO VIEW PDF VERSION OF MAP

Note: The Army Corps of Engineers requested that the contracted work be broken down and submitted to them for approval in a total of 9 work packages.

LGS is currently working on Work Package #2. This includes an area in the southern portion of the city, covering Draughan Creek from Greenwell Springs Road (south) to just south of Chervil Drive and 17 known debris sites. LGS is also encountering and removing debris between sites.

Nine of the seventeen known sites have been removed, as well as debris being encountered between sites. As of Friday (8/18/17), of 91.3 tons has been removed.

Below are some before and after photos from the work completed this week:

IBTS also continued drainage work with crews out last week cleaning out culverts and digging out ditches in several locations through out the city:

14434 Hooper Rd.

Morgan Place Subdivision

Plantation Way Subdivision: