Progress Update on Drainage Work

CLICK HERE TO VIEW PDF VERSION OF MAP
Note: The Army Corps of Engineers requested that the contracted work be broken down and submitted to them for approval in a total of 9 work packages.
Work on the following areas has been completed by LGS:
Work Package # 1 - Saunders Bayou near Greenwell Springs Port Hudson and Blackwater Roads (northern portion of City). Includes 23 known sites.
Work Package # 2 – Draughan Creek from Greenwell Springs Road south to just south of Chervil Drive (southern portion of City). Includes 17 known sites.
As of Friday (9/15/17)
LGS has continued to work on Work Packages #3 and #6.
- 32 of the known sites were removed this week.
- Debris is also being encountered between sites.
- 85 of the 219 known sites (total for all work packages) have been removed.
- 134 remaining known sites
- 262.2 Tons of debris have been removed to date
- 43,990 linear feet of channels have been cleaned to date.
Below are some before and after photos from the work completed this week:
IBTS also continues to work on drainage projects through out the City. They have been repairing and replacing culverts, digging out ditches, and spraying and weed-eating ditches in areas through out the City.