Week Ending:                       12/1/17

 

 

Areas Completed:            

 

Work Package # 1 - Saunders Bayou from northern city limit south to Gentry Lane (private drive)

Work Package # 2 – Draughan Creek from southern city limit north to Greenwell Springs Road 

Work Package # 3 – Beaver Bayou from southern city limit north to Wax Road

Work Package # 4 – Shoe Creek and un-named canals and drains from Bryce Canyon Drive north to Hooper Road

Work Package # 5 – Draughan Creek from Droze Road north to Fir Avenue and an un-named tributary starting at the intersection of Wax Road and Greenwell Springs Road north to Lawnside Avenue

Work Package #6 - Beaver Bayou from Wax Road north to approximately 3,000 feet north of Hooper Road and an un-named canal/drain near Paint Avenue.

 

 

Areas Currently Working:    

 

Work packages 7 (Hubb Bayou), 8 (Blackwater Bayou), & 9 (Blackwater Bayou)

 

Progress:

  • Total sites Originally identified = 219

  • Number of known sites removed this week = 10

  • Number of known sites removed to date = 179

  • Number of known sites remaining = 40

  • Debris is also being removed as encountered between sites.

  • Total tonnage of debris removed to date = 1,064

  • Estimated linear footage of channels cleaned to date = 104,110

Below are a few before and after photos:

 

 

 

Share on Facebook
Share on Twitter
Please reload

Featured Posts

Over $115 million in projects are coming to Central.  Click here for a list of the projects.

Nearly $115 million in projects coming to Central

August 13, 2019

1/2
Please reload

Recent Posts
Please reload

Archive