Progress Update on Drainage Work
Week Ending: 12/1/17
Areas Completed:
Work Package # 1 - Saunders Bayou from northern city limit south to Gentry Lane (private drive)
Work Package # 2 – Draughan Creek from southern city limit north to Greenwell Springs Road
Work Package # 3 – Beaver Bayou from southern city limit north to Wax Road
Work Package # 4 – Shoe Creek and un-named canals and drains from Bryce Canyon Drive north to Hooper Road
Work Package # 5 – Draughan Creek from Droze Road north to Fir Avenue and an un-named tributary starting at the intersection of Wax Road and Greenwell Springs Road north to Lawnside Avenue
Work Package #6 - Beaver Bayou from Wax Road north to approximately 3,000 feet north of Hooper Road and an un-named canal/drain near Paint Avenue.
Areas Currently Working:
Work packages 7 (Hubb Bayou), 8 (Blackwater Bayou), & 9 (Blackwater Bayou)
Progress:
Total sites Originally identified = 219
Number of known sites removed this week = 10
Number of known sites removed to date = 179
Number of known sites remaining = 40
Debris is also being removed as encountered between sites.
Total tonnage of debris removed to date = 1,064
Estimated linear footage of channels cleaned to date = 104,110
Below are a few before and after photos: